Project Records

3.6 MWp

Installed capacity

5410

PV Modules Installed

10

Inverters Installed

100%

Completion on time

4

Months duration

Project Gallery

Project Description

TIS delivered 3.6 MWp out of 7 MWp available capacity. this project gives some challenges such as ground elevation, underground cable laying system, medium level of rocks to extreme weather in between Feb-Apr. A total peak of 62 manpower working in a team to finish the project on time.

Project Details

Capacity       : 3.6 MWp

PV Module   : Canadian Solar 655 W

Location       : Pasuruan 

Duration       : Feb-Jun 2022